View before scaffolding & delivery of supplies.
 The tile
is removed from the lower front roof

Access
to the front entrance is limited and guarded during construction

Down to
the plywood deck

Dumping
the old roofing materials

New underlayment
rolled out and in place. This surface is adequate to protect
the building for up to 6 months while the new tile is delivered
and installed.

Opposite
side gets old tile stripped

Old tiles
stacked for removal. Most are broken or damaged and could
not be salvaged. 
All of
the lower areas have the new underlayment in place. Part of the
upper roof on the right has also been stripped and the new
material installed.
It is planned
that the front area will be completely stripped in the next few
days so he entrance can be reopened. Work on stripping the sides
and back will continue with some entrances needing to be blocked
at times. Once the tiles are all removed the flat roof area
will be rebuilt and then the new tiles will be installed.
The estimated time to completion is 90 days or about mid April
depending on the weather. |