1/3/07
It's a new year and the projects, both new and old, are
underway

The construction
fence near the RALPH Building comes down as work progresses.

The rear
of the old laundry soon to be removed. Temporary location
for the new HVAC units. 
The fencing
is moved by the old Laundry in preparation for demolition.

Also
in the same area the demolition of the tile roof of Building
5 begins.

Due to
limited staging area the building will be shut down to
guests while the removal is underway.



 Once
demolition is done and the building dry it will reopen.

The center
of the game room is emptied for the temporary front desk.


Out front
the dumpster is in place, the signs redirecting guests
are in place.


Only
the fish remain

Charlie
gets a new view and greets the guests

Welcome
to Cypress Pointe temporary front desk
Much
more to come. Check back frequently.