1/16/07
The new lobby flooring is started



It is
exacting work and this section had to be removed and realigned
after this picture was taken. Work will continue.

The walls
near completion

Some
of the designs start to appear


1/17/07
Progress on the floor


Moving
toward the Guest Services area 
Behind
the staircase all lined
up correctly now 
Morning
shot 1/17 
Toward
the end of the day the Guest Services area and the main
entrance have new flooring

The newfront
entry doors had to be sent back for additional hardware
installation and will be installed in early February


New header
over the Guest Services area to match the front desk

Over
the front desk the new "roof" starts to take shape

In the
restrooms the flooring work also continues



The entryway
Much
more to come. Check back frequently.