2/10/07 Its been awhile so lets get caught up on the progress

The base for the new driveway on the Lake Street side gets prepared

Drive will have one way traffic from the west, through a gate.

The old laundry is completely gone - looking toward the resort

Looking toward Lake street

Earlier this week the new lobby furnishings and art work arrived

Items placed around their future locations

Friday the art is hung, the furniture in place. The lobby nears completion

Near the front entry doors

Charlie's view near the Game room (looks like someone already had their coffee there. Soon they will have Starbucks® brand from the new Café Pointe to enjoy)

Sitting area near the Gift Shop/ Game room

Charile's former location under the stairs

Charlie's new cage and location at the lobby center

Front desk area by elevator

End of front desk by Guest Services/Office door

Plants help define seating areas

Friday update on the new building work. Levels established for the driveway

Looking toward the resort - new cart path base

The new driveway cut for base material

Looking toward the future driveway exit area

Future cart path and reopened, landscaped area between new RALPH Building and Building 5

Resort side of future cart path

View from resort of future path and area to be landscaped

Another shot of the driveway construction

Preparing the exit end to match the roadway.

Much more to come. Check back frequently.