12/1/06 The tile roof nears completion.

The windows have been installed

The pool deck gets it's cleaning and resealing work

and the trees get a haircut

Inside the laundry area is powered for the first time.

Work continues on the various safety and operational controls

It is estimated that the first batches of laundry will be done in our new facility by 12/10/06.

Much more to come. Check back frequently.